Our delivery is typically based around three straightforward agreements covering Application Engineering, supply of Hardware prior to series production and Series Production supply.
An early priority is to ensure that these dovetail into the overall client project. The project plan scope and duration depend on the product’s Purpose and chosen Product Level.
Our simple plan overview tool below allows you see an initial assessment of what your project plan might look like depending on its purpose and product level..
Purpose/quantity definitions
The production contract covers the supply of motors, inverters or integrated assemblies in volume. It typically comprises two parts, a Supply Agreement covering the commercial arrangements and the final specification to be supplied, and a Production/Batch Schedule.
For initial assessment we categorise the purpose for which products will be used.
Demonstration
Typically a small number of units (1-10) to support a client proof of concept phase.
Small batch production
Used for many specialist applications, a single-make race series or special vehicles for example (11-50 units).
Series production
Higher production volumes with end products typically sold to the public.
Tailor the production process results for your enquiry by selecting the appropriate purpose and motor level below.
Demonstration / Level 1 – Stock
- Engineering
- Hardware
- Production
Demonstration / Level 2 – Configured
- Engineering
- Hardware
- Production
*Configured parts. **Long lead stock commences prior to Gate 4.
Demonstration / Level 3 – Custom
- Engineering
- Hardware
- Production
*Long lead stock commences prior to Gate 4.
Batch / Level 1 – Stock
- Engineering
- Hardware
- Production
*Helix and/or client based. **Duration TBC as batch size specific.
Batch / Level 2 – Configured
- Engineering
- Hardware
- Production
*Configured parts. **Stock long lead can start prior to Gate 4. ***Helix and/or client based. ****Duration TBC as batch size specific.
Batch / Level 3 – Custom
- Engineering
- Hardware
- Production
*Stock long lead can start prior to Gate 4. **Helix and/or client based. ***Duration TBC as batch size specific.
Series Production / Level 1 – Stock
- Engineering
- Hardware
- Production
*If application specific requirements apply
Series Production / Level 2 – Configured
- Engineering
- Hardware
- Production
*Configured parts. **Stock long lead can start prior to Gate 4. ***Duration dependant on volume.
Series Production / Level 3 – Custom
- Engineering
- Hardware
- Production
*Long lead time stock can commence prior to Gate 4. **Duration depends on volume.